Meadowside School, Quedgeley, Gloucester

Meadowside School

Meadowside Primary School Quedgeley was funded by Gloucestershire County Council.

2200 m2 of Aquaflow was used in the car parking and playground area. A tanked system was developed collecting water and using it to flush lavatories. An increased depth of the sub base was utilised by designers to provide greater storage volume.

Since opening it has been stated that only harvested water (from the tanked system) has been used to flush the lavatories.

Site: Meadowside School, Quedgeley, Gloucester

Area of Formpave: 2200m2 of Aquaflow for car parking and playground use

Type of system: Tanked system incorporating water harvesting for lavatory flushing.

Client: Gloucester County Council

Consulting Engineer: W S Atkins

Contractor: Beam Construction, Cheltenham

Completion date: 2000

Notes: Upon visiting the school, it was stated that since the opening day, only harvested water had been used to flush the lavatories.